BUILD-OPERATE-TRANSFER PROJECTS

The Atatürk Airport International Terminal is one of the most important projects that DHMİ has undertaken. The Atatürk Airport's BOT project consisted of an international terminal building, a multi-story car park and complements. The total cost of this project was 400 million USD. The company TAV operated the terminal from 10 January, 2000 to 2 July, 2005.

The 264,000 m2 terminal building in this project, has a capacity of 20 million passengers per year, and its terminal comprises 23 passenger gates, 224 check-in desks, restaurants, a bar and duty-free shops serving for the comfort of the passengers. In addition, the project comprises a heating center, spare energy center, trash refinery, water tank, additional apron and 7076 car capacity multi-story car park, all equipped with the most up to date systems.

The operation of İstanbul Atatürk Airport International Terminal has been a great success. The terminal's operation by TAV ended on 2 July, 2005. Prior to this date, very difficult procedures were completed in order to give the private sector operational rights, both at İstanbul and the other BOT terminals, via tenders, and finally the necessary legal applications were made.

Therefore, the operational rights of all the BOT terminals, the operation periods of which have expired, have been allowed to be transferred to private sector companies.

In the first application, following the tender, the operational rights for the İstanbul Atatürk Airport Domestic and International Passenger Terminals have been transferred to TAV for 15 and a half years with a lease amount of 3 billion USD.

Another important BOT model project is Antalya Airport International Lines Terminal Building and complements. The construction works of the new International Lines Terminal Building and complements was put out to tender to serve 5 million international line passengers in 1993.

The 54,000 m2 terminal opened to service on 1 April, 1998. It comprises 12 passenger gates, 60 check-in desks, restaurants, a bar and duty-free shops serving for the comfort of the passengers. In addition, the project has a 725 capacity multi-story car park. The total cost of this project was 65 million USD, and the operating company is Antalya Airport International Terminal Management, who will operate the terminal for 9 years. The terminal will return back to DHMİ on 15 September, 2007. Because of the immense increase in the number of international passenger, the new international terminal has turned out to be inadequate, and a second terminal building was constructed under the BOT model and was given to service on 7 April, 2005.

The 91,454 m2 terminal building comprises 12 passenger gates, 45 check-in desks, restaurants, a bar and duty-free shops serving for the comfort of the passengers. In addition, the project has a 750 capacity multi-story car park. The total cost of this project was 85.5 million USD. The operative company is ÇELEBİ-IC Antalya Airport Terminal Investment and Management. They will operate the terminal for 3 years, 5 months and 26 days. The terminal will return back to DHMİ on 28 September, 2009.

Being the capital city airport, Esenboğa Airport plays an important role among the other airports of DHMİ General Directorate. The Esenboğa Airport New Domestic-International Lines Terminal Building and multi-story car park project went out to tender on 12 April, 2004 and the TAV Esenboğa Investment, Construction and Management Company won the project, giving an operation time of 15 years and 8 months. The 167,000 m2 terminal building in this project has a capacity of 10 million domestic and international passengers per year. It has 18 passenger gates, 105 check-in desks and a 4000 capacity multi-story car park. The total cost of this project is 188.7 million USD with an investment period of 36 months. The expiry operation date is 25 September, 2007.

Construction of a new international terminal building for Adnan Menderes Airport under BOT model has been continuing. The construction company is İZMİR Adnan Menderes Airport International Terminal Construction Management and Investment, and their operation period is 6 years, 7 months and 29 days. The total cost of this project is 125 million USD with an investment period of 24 months. The expiry operation date is 27 May, 2007. This project comprises a 107,899 m2 enclosed area, with a capacity of 5 million passengers annually, a terminal building with 9 passenger gates, 60 check-in desks and a 2200 capacity car park.

Construction of the Dalaman Airport new international terminal building has begun. ATM Airport Construction and Management is the construction company of the project and their operation period is 6 years, 5 months and 20 days. The total cost of this project is 72.4 million USD. The investment period is 24 months. The expiry operation date is 30 July, 2006. This project comprises a 95,587m2 enclosed area with a capacity of 5 million passengers annually, a terminal building with 7 passenger gates, 60 check-in desks and a 1000 capacity multi-story car park.

For the realization of Milas-Bodrum Airport's International Terminal Building by a BOT model, tendering studies are still continuing. This project comprises a 95,927m2 enclosed area with a capacity of 5 million passengers annually, a terminal building with 8 passenger gates, 66 check-in desks and a 786 capacity multi-story car park.